Before a new or retrofitted switchgear panel is energised, a set of checks decides whether it can be handed over safely. These are not a substitute for the manufacturer’s commissioning procedure or the local regulations, but they are the items a buyer or project engineer should see evidence of before signing acceptance.
Documentation first
- As-built drawings, including the single-line diagram and the panel arrangement.
- Routine test reports for the breakers, switches and instrument transformers.
- Relay settings and the protection coordination study.
- Type test certificates for the switchgear design and the main components.
- Nameplate data for each breaker, matched to the panel schedule.
If the documents are incomplete, the physical tests are harder to interpret. Check the drawing revision against what is installed before starting.
Mechanical checks
Operate each breaker and switch through its full travel, including the withdrawable positions where applicable. Confirm the interlocks: the breaker cannot be racked with the door open or closed as designed, the earthing switch cannot close on a live circuit, and the disconnector cannot operate with the breaker closed. Check the position indicators against the actual contact state, not only against the label.
Insulation tests
Measure insulation resistance of the main circuit and, where specified, perform a power-frequency withstand test on the main and auxiliary circuits. Record the values and the test voltage. Compare with the routine test report; a large difference between phases or against the factory value deserves investigation before energising.
Circuit resistance and contact checks
Measure the main circuit resistance across each pole and compare with the manufacturer’s reference. A high reading points to a loose joint, a worn contact or a poor connection at the cable termination. Check the torque of the main connections and the cable lugs after the measurement.
Control and protection circuits
- Test closing and opening from the panel and from remote control.
- Confirm the anti-pumping function and the trip circuit supervision.
- Check the auxiliary contact signals at each position, including the test position.
- Verify the protection relay trip path operates the breaker, not only the relay output.
A breaker that closes and opens from the panel but not from the protection relay is not commissioned. Test the trip path end to end.
Earthing and safety
Confirm the panel earthing connections, the earthing switch operation and the continuity of the earthing path. Check the door interlocks, the covers and the barriers. Verify that the voltage indication system, where fitted, shows the correct state before and after energising.
Energising and after
Energise in the sequence defined by the switching programme, with the protection in service. After energising, check the phase rotation, the voltage and current readings, and the relay measurements against the expected values. Record the results in the handover document and keep a copy with the panel.
FAQ
Who should witness the tests?
The party responsible for acceptance, together with the commissioning engineer. The exact requirements depend on the contract and the local authority having jurisdiction.
Can the insulation test replace the routine test report?
No. The routine test at the factory covers conditions that a site test cannot reproduce. The site test confirms the installation, not the design.
What if one pole reads higher resistance?
Investigate before energising: check the joint torque, the contact condition and the connection at the cable termination. A single high pole is a warning, not a rounding error.
Browse the medium voltage switchgear and vacuum circuit breaker categories, or read the VCB retrofit checklist for the interface items to verify before delivery. Send the test data through the contact form if you need a review.